Piping Maintenance Pipelines-completed Client: Eni Iraq / Ministry of Oil Location: Iraq Value: 2,800,000 USD Starting Work: 2012 Share This Tweet Share Share Email Related Posts Building and Executing Underground Piping & Sewer System for (Hay Al Qaem in Qibla district) in Basra Client: Basra Reconstruction Unit Location: Basrah Value: 11,400,000,000 Iraqi Dinars Work Period: April 2011 –… M&P + civil foundation installation 4 km flow line – size 6″ Client: BP Iraq/Rumaila Operating Organisation (ROO) Location: Rumaila Oil Field Value: 6,755,980.00 USD Starting Work:… Basra – Al-Zubair—Burjsia Project Implementation is scheduled for 2 years. Total cost of the project: $3,600,000 US Dollar.
Building and Executing Underground Piping & Sewer System for (Hay Al Qaem in Qibla district) in Basra Client: Basra Reconstruction Unit Location: Basrah Value: 11,400,000,000 Iraqi Dinars Work Period: April 2011 –…
M&P + civil foundation installation 4 km flow line – size 6″ Client: BP Iraq/Rumaila Operating Organisation (ROO) Location: Rumaila Oil Field Value: 6,755,980.00 USD Starting Work:…
Basra – Al-Zubair—Burjsia Project Implementation is scheduled for 2 years. Total cost of the project: $3,600,000 US Dollar.