EPC School Construction education-completed Client: Missan Governorate Location: Missan Value: 500,000.00 USD Work Period: 2008 (300 days) Share This Tweet Share Share Email Related Posts Building a primary school in Missan Al-BasrahEurolane was contracted by the governorate of Missan to construct a primary school. Works Included… Construction of the Shatt Al Arab College BECO supported the efforts of the College on an Engineering, Procurement and Construction (EPC) basis,… Reconstruction of the Shatt Al Arab College Faculty Client: Council of the Governorate of Basra Location: Basrah Value: 580,000,000.00 Iraqi Dinars Work Period:…
Building a primary school in Missan Al-BasrahEurolane was contracted by the governorate of Missan to construct a primary school. Works Included…
Construction of the Shatt Al Arab College BECO supported the efforts of the College on an Engineering, Procurement and Construction (EPC) basis,…
Reconstruction of the Shatt Al Arab College Faculty Client: Council of the Governorate of Basra Location: Basrah Value: 580,000,000.00 Iraqi Dinars Work Period:…